14-03-2025
- Brick wall construction is complete
- Installation of the septic tank and underground water reserve tank is complete
- Roof framework and roofing are complete
- Currently, the installation of electrical, plumbing, and communication pipes in the walls is underway in preparation for wall plastering


14-02-2025
- All concrete structural work is completed, including the foundation, ground beam, 1st floor, and concrete columns to support the roof
- Concrete work on the swimming pool structure is complete
- Currently working on the roof steel frame


20-01-2025
- The foundation has been completed
- The ground beams are finished
- The construction of the swimming pool structure has been completed


17-12-2024
Construction camp and plot number 3 foundation preparations for Villa Type A are ongoing