01-09-2025

Interior ceiling work completed Exterior ceiling work completed Interior tiling completed Interior and exterior painting completed SPC flooring in bedrooms completed Swimming pool work completed Interior door and laminate work completed Glass and aluminum work completed Interior electrical work completed Sanitary ware and water pump installation completed Built-in furniture and curtains will be completed this […]

17-07-2025

Interior ceiling work completed Exterior ceiling work 80% completed Interior tile work 100% completed Bedroom floor work, cement leveling ready for SPC sheets Swimming pool tile work starts next week with water pump system work Interior door work, laminate material is in progress Glass and aluminum work will be installed next week Interior electrical work […]

16-06-2025

Interior ceiling work has been completed Plastering of the perimeter fence has been completed Tiling work is currently in progress Interior doors have been ordered Glass and aluminum materials have been ordered Installation of the house’s drainage system has been completed Project-wide drainage system has been completed Underground electrical conduit installation is in progress The […]

13-05-2025

Interior and exterior wall plastering: Completed Primer painting on house walls: Completed Installation of electrical, plumbing, and communication conduit systems within walls and ceilings: Completed Interior and exterior ceiling work: In progress Perimeter fence masonry work: Completed Tiling work: Scheduled to begin next week (materials are currently being delivered to the site) Plastering of the […]

12-04-2025

Interior and exterior wall plastering has been completed Installation of electrical, plumbing, and communication conduit within the walls has been completed

14-03-2025

Brick wall construction is complete Installation of the septic tank and underground water reserve tank is complete Roof framework and roofing are complete Currently, the installation of electrical, plumbing, and communication pipes in the walls is underway in preparation for wall plastering ผนังก่ออิฐ เสร็จแล้ว งานวางถังบำบัดน้ำเสีย และถังสำรองน้ำใต้ดินเสร็จแล้ว งานโครงหลังคา และมุงหลังคา เสร็จแล้ว ขณะนี้กำลังดำเนินการฝังท่อระบบไฟฟ้า สุขาภิบาล และสื่อสารในผนัง เพื่อทำการฉาบปูนผนัง

This website uses cookies to sweeten your experience. By continuing, you consent to our use of digital crumbs.